Friday, October 23, 2009

Production Schedule Update

While the weather seems to be letting up a little bit in regards to the deluge of precipitation we have had the last few days, colder weather has settled in for today and is going to significantly hinder our ability to install and produce output from a production perspective. While the weekend seems to tease us with a little break from these conditions, next weeks weather looks to be similar to what we have seen the last few days. With the current weather pattern persisting, communication and flexibility will be the key to maintaining the production schedule.

This is your production schedule update for Friday October 22, 2009:


Siding: 3-4 Weeks

Windows: 8 Weeks

Roofing: 1.5 Weeks (Weather & Material Dependent)



Current Jobs:

Pat Emge: Van Stratten Job (09-2014) 6214 Cty Rd P39 Ft. Calhoun NE

Mark Rasmussen: Selee Job (09-6004) 23180 Dutch Hall Rd Bennington NE

Craig & John: Walker Job (09-3022) 16006 Wakeley Plaza Omaha NE

Gary Dukat: Sporhase Job (09-2015) 15102 Redman Ave Omaha NE



Upcoming Jobs:

Pat Emge: Balaban Job Warranty Work

Mark Rasmussen: James Job (09-3016)

Craig & John: O'Conner Job (09-4004)

Gary Dukat: Pecha Job (09-2017)

Russ Newman: Schlueter Job (09-0001)

Rodrigo Moreno:

- Tomaso (09-6005) Tuesday 10/27

- Padilla (09-3026) Thursday 10/29