Wednesday, October 14, 2009

Daily Production Update

Good morning everyone, here is your daily production update for Wednesday October 14th 2009. While the weather is really throwing a wrench into the system, we are steadily moving forward through the week. Long term forecasts for next week are looking like the weather will get a little warmer and dry out, hopefully that holds true.


Siding: 4 Weeks

Windows: 8 Weeks

Roofing: 1.5 Weeks (Dependent on Weather & Material Availability)



Current Jobs:

Pat Emge: Kazantseva Job (09-3017) 6217 N. 131st Avenue, Omaha NE

Mark Rasmussen: Smith Job (09-3014) 5942 North 110th Street, Omaha NE

Craig & John: Nachun Job (09-4021) 1634 North 75th Street, Omaha NE

Gary Dukat: Salinas Job (09-5006) 21421 Greenbrier Drive, Elkhorn NE

Russ Newman: Taylor Job (09-3015) 325 Stevens Circle, Council Bluffs IA




Upcoming Jobs:

Pat Emge: Balaban Job

Mark Rasmussen: James Job

Craig & John: O'Conner

Gary Dukat: Bentley Job

Russ Newman: Selee Job

Rodrigo Moreno: Yost Job

Dan Justensen: