Thursday, August 27, 2009

Husker Production Update 8/27

Good morning ladies and gentlemen, as we approach the 11th hour we wanted to take a moment to keep you all updated on our production schedule and some revisions that we have made to it. As a result of losing a crew, having to accomodate the flub in the scheduele as a result of losing that crew and also trying to finish out the New Husker Office Facades, we are now looking at a 6-7 week production schedule for siding and windows.

Aside from the deluge of water and a cool and damp start this morning, we are keeping our fingers crossed for the the weather to break this afternoon and carry us through the weekend. Highs in the upper 70's and lower 80's with minimal percipitation chances are expected for our glorious exodus into our new facilities over the next few days. Any questions regarding our production schedule for the duration of our move would best be presented in person to the production staff and their associates. Have a great day!



Siding: 6-7 Weeks

Windows: 6-7 Weeks

Roofing: 2-3 Weeks



Current Jobs:


Pat Emge: Timmins Job (09-056) 4844 Woolworth Avenue, Omaha NE

Mark Rasmussen: Husker Office Facades / Elkhorn NE

Craig & John: Frazer Job (90-002) 3200 Avenue A, Council Bluffs IA

Gary Dukat: Coufal Job (09-2006) 15417 Harney St, Omaha NE

Russ Newman: Suhr Job (09-2009) 304 South 54th St, Omaha NE





Upcoming Jobs:


Pat Emge: Butler Job (09-061) 151 Ginger Cove, Valley NE

Mark Rasmussen: Moore (09-2013) 2515 South 37th, Omaha NE

Craig & John: O'Conner Job (09-4004) 9744 Fieldcrest Drive, Omaha NE

Gary Dukat: Pratt Job

Russ Newman: Frazer Job (90-002) 3200 Avenue A, Council Bluffs IA

Rodrigo Moreno: Morgan Job (09-4013) 3518 South 98th Street, Omaha NE

No comments: