Good morning everyone, after a significant delay in production due to extreme weather related conditions we are looking to get back on track today. The 3 days of snow and cold that we have endured has essentially pushed the entire production schedule back accordingly. The weather does look to be steadying a bit after this latest fiasco and after a couple of small chances for freezing rain and drizzle this weekend, next week looks to be at least calm weather wise.

Partly sunny to sunny skies are forecast with temperatures holding steady in the mid to upper teens through Wednesday of next week. Long range models are showing a moderation in temperatures as we approach next Thursday with the high possibly approaching freezing (32). While these cold temps put a damper on installation efforts, we are now able to move forward at getting back on schedule.

Good day!

Siding: 1 Week (Pending Material & Weather)

Windows: 8 Weeks

Roofing: Looking alot like March 1st



Current Jobs:

Pat Emge: Idle

Mark Rasmussen: Kunkel Job (09-1003) 3306 south 122nd st. omaha

Craig & John: Janda Job (09-3028) 10535 monroe st. omaha

Gary Dukat: Pysh Job (09-5011) 12130 P st. omaha (Right by Trents house)

Russ Newman: Idle

Rodrigo Moreno: Idle

Dan Justensen: Idle




Upcoming Jobs:

Pat Emge: Idle

Mark Rasmussen: Tichenor Job (09-5010)

Craig & John: Idle

Gary Dukat: Ray Job (09-3020)

Russ Newman: Lambrecht (09-6003) (Mon. 12/14 Start)

Rodrigo Moreno: Idle

Dan Justensen: Idle