Good morning everyone, this is your Production Schedule Update for Wednesday, November 4th 2009. The skies are clear and the temperature is rising and with that our ability to move through another week of production with mother natures cooperation. Long range forecasts are looking great heading into this weekend with temperatures holding steady in the mid to upper 60's with mostly sunny skies. Next week looks to be warm as well with a chance of thunderstorms and showers on the horizon for Monday and Tuesday.
While window jobs are continuing to fill the board, we are offering a deal back here in the production department for siding jobs. If you sell a siding job we can theoretically begin installation in roughly two weeks pending material availability and mother natures cooperation.
Remember, this time of year a caveat always exists; mother nature plays a giant role in installation schedules but with weather like we have this week things will keep rolling right along.
Have a great day!
Siding: 2 Weeks
Windows: 8 Weeks
Roofing: 1.5 Weeks
Current Jobs:
Pat Emge: Balaban Warranty Work
Mark Rasmussen: James Job (09-3016) 13414 Erskine St. Omaha NE
Craig & John: Horton Job Wraps & Frazer Job Fascia and Shutters
Gary Dukat: Salinas Job (09-5006) 21421 Greenbrier Drive Elkhorn NE
Russ Newman: Horton Job (09-5004) & Giebler Job Touch Up
Upcoming Jobs:
Pat Emge: Spier Job (09-5009) 20117 Wolf Street Elkhorn NE
Mark Rasmussen: Phelan Job (09-6008) 418 Chippewa Drive Gretna NE
Craig & John: Barnes Job (09-6007) 11212 Patrick Ave. Omaha NE
Gary Dukat: Janvrin Job (09-2019) 21402 Honeysuckle Elkhorn NE
Russ Newman: Husker Windows in Showroom